Project Schedule/Updates
Here is a 2008 month-by-month look at the construction schedule. For more information contact info@I40widening.com.

January-work continues on new eastbound lane and bridges, and we will begin work on the sound wall.
February-we will complete the US19/23 bridge deck, place beams on the railroad bridge.
March-there will be a traffic shift from the on ramp from 19/23 to I40 eastbound cross the newly constructed railroad bridge.
April-eastbound traffic will shift to the new eastbound lane.
May-construction begins on new median barrier rail.
June-median lane work continues.
July-median lane and barrier work complete.
August-complete all unfinished work, place new signs, and complete project clean up.
September-open all lanes!